INTERFLO 150 - Teniente 8, Chile

In the main haulage level of El Teniente, INTERFLO 150 controls 9 trains hauling copper ore on a 22 km long line, loading two different types of ore from 25 locations and unloading in four different locations. The implementation of our system has enabled an output increase of 155% from approximately 55,000 tonnes a day to 140,000 tonnes a day.